The method

Four steps, in order.

The tabs inside an investigation follow the method. Someone who works left to right has done a proper root cause analysis, even if nobody ever taught them one.

  1. State the problem

    What, where, when, how big. Facts only, no causes yet.

  2. Fishbone

    Spread wide: list every possible cause on six bones.

  3. Five whys

    Drill down from the likely cause until you reach something you can change.

  4. Act, then verify

    Assign actions with an owner and a date. Weeks later, check the number really moved.

Fishbone diagram

Spread wide before you dig deep.

Also called an Ishikawa diagram. Six fixed bones make the team think about every kind of cause, not just the first one somebody said out loud.

ProblemPress 2 stopped 3×PeopleNew starter on nightsNo handoverMachineRelay set for old motorOverdue serviceMaterialNew supplierMethodNo motor-swap checklistMeasurementCounter not calibratedEnvironmentHot afternoon shift
Example fishbone. The red dot marks the cause the team thinks is most likely.
BoneThe question it asksExamples
PeopleWho was doing the work, and what did they have to go on?New starter, no handover, two machines on one pair of hands
MachineWhat about the equipment itself?Worn bearing, wrong setting, overdue service
MaterialWhat went into it?New supplier, damp batch, wrong grade
MethodHow is the job meant to be done, and is that how it is done?No written changeover, step skipped under pressure
MeasurementHow do we know? Could the numbers be wrong?Gauge out of calibration, counter miscounting
EnvironmentWhat was going on around the job?Heat, damp, poor light, night shift

Mark a cause as likely, and add the evidence for it. A cause without evidence is shown as still a suspicion.

Five whys

Keep asking until you reach something you can change.

The press stopped. Why?Because the motor tripped
Why?Because the overload relay opened
Why?Because it is set to 8 amps and the motor draws 10
Why?Because it was set for the motor this one replaced
Why?Because nothing in the motor swap asks anyone to check the relay

The fifth answer is the root cause. The fix is a line on the motor-swap checklist, not a new relay. Five is a habit, not a rule: add a step only when you have an answer for it. And the answer is never a person's name; ask why it was possible to forget.

Countermeasures and verification

Fix it for good, and prove it.

Containment

Stops the damage today, such as sorting stock by hand. Does not fix the cause.

Corrective

Removes this cause on this machine, such as resetting the relay.

Preventive

Stops the same cause appearing elsewhere, such as checking the other presses.

One owner, one date

Every action has one person and one due date, so a late action shows as late.

Verify

Weeks later, look at the same number. If it did not move, go back to the fishbone.

Start where you notice it

Raise an investigation from a stop, an alert or a bad batch. The details are filled in for you.

One investigation per problem

If three people press Investigate on the same stop, they all join the same one.

Everyone can join in

Anyone signed in, including operators, can read and comment.

See Nisthora on your own machines.

Book a demo. We will show you live data and talk through your machines, lines and shifts.

Book a demo